Knapp Street Connector Trail

Grand Rapids Township and Ada Township have collaborated to build a trail connection between the two townships. Moore & Bruggink helped the townships obtain a Transportation Alternatives Grant from the Grand Valley Metro Council and the Michigan Department of Transportation, providing a large portion of the funding. Moore & Bruggink provided all design engineering and topographic survey for the project, and is currently providing delivery engineering, inspection, and construction staking services. Construction of the project began in September of 2013. The site has been stabilized for the winter. Completion of retaining wall construction and final paving is planned for April and May of 2014. When complete, this trail will connect approximately 37 miles of existing trails and sidewalks within the two townships.

Check Out The Progress